Controlled Asbestos Removal

Follow the Wandsworth Build

“The earlier you commission an asbestos survey, the better. It gives you time to get comparable quotes, assess your options, and, if high-risk notifiable asbestos is identified, plan for the HSE notification period, crew mobilisation, and full removal under controlled conditions. All of this has to be done before demolition begins, so if you have vacant possession, don’t delay.”


Oliver Steele-Perkins, Chartered Construction Manager

Preparing for safe removal of asbestos

Construction site with safety barricades displaying environmental company branding, white tarps, and safety warning signs, with trees and buildings in the background.

The project has entered a critical phase of site preparation, covering temporary infrastructure, safety measures, and ecological responsibilities. Asbestos removal is being carefully planned and managed in line with HSE regulations — a vital step before demolition can begin.

Following the required 14-day notification to the Health and Safety Executive (HSE), we mobilised on-site as scheduled and in line with the overall project programme. The asbestos-containing materials identified in the pre-demolition survey included external soffits and fascias, which necessitated full enclosure.

Controlled, safe and compliant

A safety enclosure with black and yellow striped borders, containing signage that reads 'Enclosure Viewing Panel' and warning signs including 'No access for unauthorized persons,' 'Respiratory equipment must be worn,' and 'Safety overalls must be worn.'

In accordance with the Control of Asbestos Regulations 2012, a licensed contractor was appointed to undertake the works, ensuring that all procedures followed strict legal and environmental protocols.

A purpose-built enclosure was constructed to fully wrap the bungalow below the roofline, maintaining negative pressure within the work zone throughout the removal process. Air monitoring was carried out continuously, and a dedicated decontamination unit was installed on-site to manage personnel movements safely.

Monitoring, waste management and site safety

A plastic enclosure for a mask wash bucket and sponge, with a partially visible sign indicating its purpose.

Viewing panels were set up to allow safe observation of the removal process, while a clearly defined waste route ensured all contaminated material was double-bagged and disposed of in line with hazardous waste regulations.

This setup demonstrates the correct approach to licensed asbestos removal, controlled, monitored, and fully compliant from start to finish.

Asbestos removal isn’t just a regulatory step – it’s a critical part of the pre-construction roadmap. On all our projects, we programme asbestos surveys and removal well in advance of demolition. This ensures we remain compliant, keep the site team and public safe, and avoid delays. Upon completion, certification is issued and included in the Health & Safety file – a key requirement.

Planning a New Build?

Manage risk properly before demolition begins

Asbestos removal is a critical pre-construction stage that requires careful planning, legal compliance and precise coordination. Delays at this point can impact programme, cost and site safety if not managed correctly from the outset.

If you’re preparing for demolition or early site works, early surveys, contractor selection and programme alignment are essential to keeping your project on track.

We provide structured support across pre-construction planning, compliance and delivery to ensure all enabling works are managed safely and without disruption.