Demolition & Ground Clearance

Follow the Wandsworth Build

“Reaching the point of demolition is a milestone in any project. It signals that months of planning, permissions, and pre-construction coordination have been successfully navigated. Behind the scenes, it takes far more than just scheduling a machine operator for demolition, this phase is where logistics, legal compliance, and design all start to converge on site.”


Oliver Steele-Perkins, Chartered Construction Manager

Demolition and ground clearance

Asbestos removal has now been completed and the site prepared for full demolition, a milestone that follows extensive behind-the-scenes coordination.

Before you can legally begin demolition works, you are required to submit a formal demolition notice to your local authority under Section 80 of the Building Act 1984. This process ensures the safety and coordination of works and allows the council to raise any concerns before demolition takes place. Submitting a demolition notice is a critical step in the pre-construction phase.

Preparing for Piling

It’s not enough to remove just the above-ground structure. The existing foundations, legacy drainage, and any redundant underground services must also be grubbed out to create a clean, obstruction-free footprint for the new basement. This is critical to avoid unforeseen delays and costs.

Ahead of mobilisation, the main contractor will mark out the line of the new building footprint and carry out ground probing to a depth of at least 1.5 metres along the proposed piling zone. This helps confirm the ground is free from significant obstructions. If obstacles are discovered during piling works, these may result in delays, variations, and additional cost, which is why a clear and verified site handover to the groundworkers is essential.

Detailed basement design in progress - Ready for pre-start meetings

While demolition activity was underway on site, technical design development for the basement and piling progressed in the background.

The engineer and architect have been working on the detailed design coordination, essential preparation ahead of the pre-start meeting with the groundworks contractor where we’ll discuss site logistics, sequencing and preparation for the piling phase.


Planning a New Build?

Manage the transition from planning to construction properly

Demolition and ground clearance mark the point where planning, design and site delivery come together. This stage requires careful coordination of legal requirements, site logistics and technical preparation to ensure the project can move smoothly into foundation works.

If you’re approaching demolition or early construction, this is where clear programme control and site coordination are critical to avoiding delays and unforeseen costs.

We provide structured support across pre-construction and delivery to ensure each stage is properly planned, coordinated and executed on site.